Activity 1: Establishment of Working Group & Workplan |
Activity / Milestone |
Accountability |
Predecessors |
Date |
Status |
Activity 1.1: Review Job Cards |
Rapporteurs |
|
Apr 2015 |
Complete |
Activity 1.2: Initial Meeting at METP |
Rapporteurs |
1.1 |
Apr 2015 |
Complete |
Activity 1.3: Draft Workplan & Summary |
Rapporteurs |
1.2 |
Apr 2015 |
Complete |
Activity 1.4: Confirmation of subject matter experts (and associated METP Member). |
Rapporteurs |
|
Apr 2015 |
Complete |
Activity 1.5: Establish Yammer group |
B.L Choy |
1.4 |
May 2015 |
Complete |
Activity 1.6: Meeting (teleconference) |
Rapporteurs |
1.4 |
Jun – Oct 2015 |
Complete |
Activity 1.7: Finalise Workplan V1 |
Rapporteurs |
1.6 |
Oct 2015 |
Complete |
Milestone 1: Working group & workplan complete |
Rapporteurs |
1.7 |
Oct 2015 |
Complete |
Ongoing Activity: Workplan updates |
Rapporteurs |
1.7 |
Ongoing |
|
|
Activity 2: AMHS Testing of OPMET Data (Job Card CP.008.01) |
Activity / Milestone |
Accountability |
Predecessors |
Date |
Status |
Activity 2.1: Assist ICAO Communications Panel (CP) in the coordination of the arrangements between the States/Provider States, international organizations and other stakeholders in order to complete exchange tests as required for the IWXXM compliant exchange of METAR, SPECI, TAF and SIGMET. |
CP Chair and METP WG-MIE Rapporteurs |
|
Oct 2015 |
|
Activity 2.2: Establish AHMS IWXXM test criteria |
|
|
Sep 2015 |
|
Activity 2.3: Establish AHMS IWXXM test guidance material (for participants) |
|
2.2 |
Oct 2015 |
|
Activity 2.4: Identify States, Provider States and/or International Organizations to participate in exchange tests |
|
2.1 |
Nov 2015 |
|
Activity 2.5: Conduct IWXXM exchange tests over AMHS |
|
2.3 & 2.4 |
Oct-Jan 2016 |
|
Activity 2.6: Collect/publish test results |
|
2.5 |
Jan 2016 |
|
Milestone 2: Report on AMHS testing of IWXXM-compliant OPMET data |
|
2.6 |
Jan 2016 |
|
|
Activity 3: iWXXM Implementation Guidance (Job Card CP.008.01) |
Activity / Milestone |
Accountability |
Predecessors |
Date |
Status |
Activity 3.1: Review report on AMHS testing of IWXXM-compliant OPMET data |
|
2 |
|
|
Activity 3.2: Review work of WMO TT-AvXML |
|
|
|
|
Activity 3.3: Develop guidance for IWXXM implementation |
|
3.1 & 3.2 |
|
|
Activity 3.4: Review IWXXM implementation guidance |
|
3.3 |
|
|
Activity 3.5: Finalise guidance for IWXXM implementation |
|
3.4 |
Mar 2016 |
|
Milestone 3: Guidance on IWXXM implementation complete |
|
3.5 |
Mar 2016 |
|
|
Activity 4: AMHS Testing of WAFS Data (Job Card CO.008.01) – Clarify whether this is feasible |
Activity / Milestone |
Accountability |
Predecessors |
Date |
Status |
Activity 4.1: |
|
|
|
|
Activity 4.2: |
|
|
|
|
Activity 4.3: |
|
|
|
|
Activity 4.4: |
|
|
|
|
Activity 4.5: |
|
|
|
|
Milestone 4: Report on AMHS testing of WAFS data |
|
|
May 2016 |
|
|
Activity 5: AMHS Testing of other MET Data (Job Card CP.008.01) |
Activity / Milestone |
Accountability |
Predecessors |
Date |
Status |
Activity 5.1: Establish AMHS testing guidance for other MET data |
|
|
|
|
Activity 5.2: Identify States, Provider States and/or International Organizations to participate in exchange tests |
|
|
|
|
Activity 5.3: Conduct IWXXM exchange tests over AMHS |
|
5.1 & 5.2 |
|
|
Activity 5.4: Collect/publish test results |
|
5.3 |
May 2016 |
|
Milestone 5: Report on AMHS testing of other MET data |
|
5.4 |
May 2016 |
|
|
Activity 6: iWXXM Standards for METAR, SPECI, TAF, SIGMET |
Activity / Milestone |
Accountability |
Predecessors |
Date |
Status |
Activity 6.1: Review current accomplishments on IWXXM standard development and testing |
|
2 & 3 |
|
|
Activity 6.2: Identify standards that require development/clarification for METAR, SPECI, TAF, SIGMET |
|
6.1 |
|
|
Activity 6.3: Development of IWXXM exchange ConOps and use cases |
|
|
|
|
Activity 6.4: Develop SARPs for IWXXM for METAR, SPECI, TAF, SIGMET |
|
6.3 |
|
|
Milestone 6: Standards for iWXXM compliant METAR, SPECI, TAF, SIGMET complete |
|
6.4 |
Aug 2016 |
|
|
Activity 7: iWXXM Recommended Practices for WAFS and other MET Information |
Activity / Milestone |
Accountability |
Predecessors |
Date |
Status |
Activity 7.1: Identify standards that require development/clarification for WAFS and other MET information |
|
|
|
|
Activity 7.2: Further development of IWXXM exchange ConOps and use cases |
|
|
|
|
Activity 7.3: Develop SARPs for IWXXM for WAFS and other MET information |
|
|
|
|
Milestone 7: Recommended Practices for iWXXM compliant WAFS and other MET Information |
|
7.3 |
Aug 2016 |
|
|
Activity 8: MET-in-SWIM ConOps (Job Card METP.004.01) |
Activity / Milestone |
Accountability |
Predecessors |
Date |
Status |
Activity 8.1: Develop a draft MET-in-SWIM ConOps |
|
|
|
|
Activity 8.2: Review MET-in-SWIM ConOps |
|
8.1 |
|
|
Activity 8.3: Finalise MET-in-SWIM ConOps |
|
8.2 |
|
|
Milestone 8: MET-in-SWIM ConOps complete |
|
8.3 |
Jul 2018 |
|
|
Activity 9: MET-in-SWIM Roadmap (Job Card METP.004.01) |
Activity / Milestone |
Accountability |
Predecessors |
Date |
Status |
Activity 9.1: Develop a draft MET-in-SWIM Roadmap |
|
|
|
|
Activity 9.2: Review MET-in-SWIM Roadmap |
|
9.1 |
|
|
Activity 9.3: Finalise MET-in-SWIM Roadmap |
|
9.2 |
|
|
Milestone 9: MET-in-SWIM roadmap complete |
|
9.3 |
Jul 2019 |
|
|
Activity 10: MET-in-SWIM Provisions (Job Card METP.004.01) |
Activity / Milestone |
Accountability |
Predecessors |
Date |
Status |
Activity 10.1: Develop a draft MET-in-SWIM SARPs |
|
|
|
|
Activity 10.2: Review MET-in-SWIM SARPs |
|
10.1 |
|
|
Activity 10.3: Finalise MET-in-SWIM SARPs |
|
10.2 |
|
|
Milestone 10: MET-in-SWIM provisions complete |
|
10.3 |
Sep 2020 |
|
|
Activity 11: MET-in-SWIM Guidance Material (Job Card METP.004.01) |
Activity / Milestone |
Accountability |
Predecessors |
Date |
Status |
Activity 11.1: Develop a draft MET-in-SWIM guidance material |
|
|
|
|
Activity 11.2: Review MET-in-SWIM guidance material |
|
11.1 |
|
|
Activity 11.3: Finalise MET-in-SWIM guidance material |
|
11.2 |
|
|
Milestone 11: MET-in-SWIM guidance material complete |
|
11.3 |
Sep 2020 |
|